Gas Service Installation

January 27, 2019

As mentioned in an earlier post, I have changed my plans to not bring a natural gas service into the property.

We will not utilize gas for the heating system and instead plan to install an Air to Water Exterior Heat Pump which can be as high as 400% efficient in my climate.I also am a firm believer that a gas cooktop is a very poor choice given the efficiency and cooking speed of today’s inductive cooktops (for those not in the know – induction boils water WAY faster than gas – the web is full of tests showing similar results to this site) .  Having a gas cooktop is also on par with having a campfire in your kitchen due to the pollutants the flame spews into your home.

Only reason I would have wanted a gas service was to allow for a natural gas BBQ, but was not going to go through the expenditure just for that.

But then things changed on the back-up generator front.  The planned diesel generator just was not making sense.  The run time for a full tank would be less than two days, meaning if there was a real emergency where the power was going to be off several days, we would not be covered.  The diesel units are also noisier, bigger, and cost way more than the NG units.  But the most important aspect is that the NG unit burns so much cleaner than a diesel unit.

When I discovered the connection fee to the utility would be under $200 a year (cost even if we do not use any gas), the decision became that much easier and in September last fall, I applied for the gas permit and installed the gas line.

Obviously we do not want a gas meter on the front of the house and I will have a set of stairs down to the basement on the exterior of the north side, and a sidewalk right against the building on the south side, so we requested a remote meter location from the utility.  After some arm twisting they approved. The meter will go on the south side of the house about 10ft away from the house under some tall cedars.  This location is roughly in line to where the gas line service connection to the property is located. The meter location is also very close to where the outdoor BBQ pit will be located, so I will get a NG BBQ after all 🙂

Because I was close to the cedar trees and really did not want to disturb roots more than I had to, I used a high pressure water hose (district pressure) with a jet connection to trench through the roots and rocks. And when I hit native undisturbed soil, I was reminded of how rocky our main excavation was! In addition to the hydro-trenching, I also utilized the shop vac to ‘dig’ around the electrical service and phone line conduit.

With soil like this, its easier to hydro trench than dig

Once the trenching was complete, I was able to run the gas line with tracer wire.  The pipe is sized based on the Btu loads of the connected equipment.  In my case I ran a 3/4″ poly line to service the genset but also allow some expansion capacity in the future for a ‘just-n-case’.  Although the meter and BBQ are in line with where the service enters the property, the generator will be on the opposite side of the house.  So a gas line extends from the meter location across the front of the house and down the north side to the generator location.  I liked this route because it will later be under concrete sidewalks the entire way and protected.

The easiest approach when installing a gas line is to buy the stab risers and then a length of tube.  This allows you to fine tune the overall length based on the trench path taken.

End of tube are chamfered with appropriate tool.

Stab depth is marked using distance indicated on connector

Tube is stabbed into connector till mark line flush with end. Some dishwashing soap helps ease this into place.

Meter Location with branch for BBQ circuit pointing down to right and connection to meter to left. Also a stub straight out right for possible patio heater.

Once pipe was fully installed, I pressurized to 20 PSI and kept pressurized to ensure no damage occurred during backfill operations.

Inspectors wanted to see a 12″ separation between the main electrical service and gas line. Block of wood maintained this separation untill fill in with dirt and then removed.

The white PVC conduit will allow the utility to run their gas line to the meter without having to re-excavate this congested area containing the main electrical service, telephone conduit, and storm drains.

Where you are unable to surround the gas line with clean fill, free from objects that would damage the plastic pipe, it must be run inside a sleeve like shown on the north elevation where it was buried in gravel.  I used perforated BIG-O which is about the only thing this material is good for beside draining a farmers field!

Where the poly gas line cannot be surround by clean fill without rocks, it must be installed a sleeve.

Finally, once buried a few inches, cation tape is added along the length of pipe.

As always, thanks for visiting and please send us your comments or questions.

“Don’t be afraid to be ambitious about your goals. Hard work never stops. Neither should your dreams.” —Dwayne Johnson (born 1972) Actor, Producer, Semi Retired Professional Wrestler

Top ↑

Roof Insulation Package Arrived

January 20, 2019

On Friday, I received the 8 skids of ROCKWOOL COMFORTBATT® that represent the roof insulation package.

The product came directly from ROCKWOOL via train to Convoy Supply (they have a rail spur at their Coquitlam location for unloading) and then was loaded onto two Convoy trucks (one with HIAB and other with forklift) and brought to site where it was lifted onto my lower office and garage roofs (of course I checked the roof truss design loading to make sure the skids did not exceed designed live load).

8 Skids of COMFORTBATT (mainly 3.5″ thick on this side – Office Roof)

Another 5 skids on the Garage roof (All 5.5″ R22 for 24″ Spaced framing)

Convoy crew getting ready to unload.

The roof insulation package will consist of 2 layers of 3.5″ R14 and 2 layers of 5.5″ R22 for a total depth of 18″ providing an effective R62 assembly based on framing losses (nominal R72).  I am able to completely fill the rafter space because I installed cross-purlins, with 1″ spacer blocks, above the truss surface to provide the cross ventilation and the code required 2.5″ between the roof sheathing and insulation surface.

Roof cross ventilation provided by cross-purlins and 1″ spacer blocks.

I also plan to eek out every bit of R-value possible from the assembly by filling the truss triangles with some 1.5″  ROCKWOOL COMFORTBOARD™ 80 material.

I will proceed on this installation once I have received authorization from the engineers and Municipality, which is expected early this coming week.

I want to thank Alejandra Nieto of ROCKWOOL and Brian Picco of Convoy Supply – Coquitlam for their coordination in setting up this shipment. I especially want to thank Antoine Habellion of ROCKWOOL for his continued support of theEnclosure.

And as always – to those of you visiting my site – Thank-You and please submit your comments and questions.

Top ↑

Final Lap – We Hope!

January 13, 2019

Happy New Year

First, Happy New Year to all in Internet Land, hope everyone had a great Christmas.

Sorry Folks – I know it has again been a way too long since my last update! I’ve had a lot on my plate, and have been running on fumes lately, so the last thing I seem to be able to do is sit down at the computer at night to write an update. I resolve to do better for 2019!

There has been too much done since last update to provide detail reporting on it in one post. So I will provide a synopsis here and then provide separate updates as able, to cover tasks completed with detailed photos.

Cedar Cladding Complete

The first completed task I am thrilled to report, is that on Friday I installed the last piece of horizontal cedar siding on the house.   This has been a task that I though would never be complete.  I originally budgeted 3 months to install the Delta Vent – SA Water/Air barrier membrane,  6″ of exterior ROCKWOOL mineral wool insulation, and the Coulson engineered T&G cedar siding.  This was HEAVILY optimistic and in reality this has taken just over 1300 hours to complete! I still have the window returns to complete on the first floor which should take 3-4 days to complete (they are some big windows).

On a side note, to date I have put in 8376 hours into this project (does not include some of the deconstruction time as before I kept a time sheet, also does not include any hired casual labour, blogging time, and most of my online research time)

Installing exterior insulation significantly increases the detailing efforts around all penetrations.  But the real time drain was my siding design itself.  I was looking for a nice clean look with no trim work, so ALL edges and seams have been mitred.  Every piece of wood has a mitre at both ends.  The corners were cut at 48°.  Over cutting the mitre ensures that if the corner is out of square at all, the outside tip of the mitre still meets tightly.   All of the splices on the long runs were also cut at 15° to help prevent water entry at but joints and provide a better look.   To ensure the outside wall and window return corners were plumb, this involved cutting the mitre on one end, temporarily placing the strip in place to accurately mark the other end, before taking back to mitre saw to cut last mitre. The tolerances needed for a tight attractive joint are far too tight to rely on a measured cut line. The cut ends are then re-stained before permanently blind stapling into place.  This monotonous repetition went on day after day, but the end result was worth it (I think!).

Looking at the North West corner of the dwelling. Design of house accommodated a mature cedar at this location.

Looking at front east side of dwelling. The lower and upper unfinished walls will be finished with a different cladding to provide some diversity and architectural interest to the viewing public.

Mitred siding window returns provide a nice clean look. Also note that the majority of window frame is hidden. This allowed for insulation to be placed on the outside surface of the window to increase the overall installed thermal resistance of the assembly. One build is complete, I will model how much better this approach is and provide feedback on this journal.

Inside corners were butted up against each other and then seam covered with a 1/2″ x 1/2″ triangular corner bead.

This photo shows the siding with just the Cetol 1 base coat (top left) and then the additional 2 coats of Cetol 23. The finished is a much richer appearance. Also note the clean mitred corner. Vent termination will be exhaust from the metal work shop below the garage

Soffits

The soffit design was determined and has been completed on the north exposure, clerestory, and most of the west exposure. I chose the use Coulson Cedar again as the quality is excellent and it is well below the cost of the locally available solid cedar (and looks better as well).

The design incorporates full length venting. We also had to ensure that the top of wall rain-screen venting air, in case it had a high moisture load, would mix well with outdoor air before being drawn into the roof venting system. This was done by blocking the rain-screen cavities and forcing the air to exit about 6″ below the surface of the soffit and installing the roof venting strips on the outboard side of the soffit.

Completed soffit with full length vent strip on right and rain-screen top venting on left. Nice clean modern look.

Top of the wall rain-screen venting system.

Above photo shows the top of wall rain-screen venting termination.  In foreground the perforated SS bug screen is visible. Blocking terminating the rain screen cavity is attached to underside of roof trusses up tight again insulation (metal flashing is installed to close off the rain-screen cavity in areas where the blocking was not tight to insulation due to construction variances).  Finally the cedar siding skirt is attached to the blocking to force the escaping humid air down and around before exiting cavity.  Underside of blocking and the insulation face are painted a dark brown to provide good site lines when visible from below.

Misc Tasks

While the wall envelope including membrane, insulation, and cladding occupied the vast majority of my time over the last three months, I also snuck in and completed a few other tasks.

To aid in maintenance of the roof surfaces down the road, a permanent ladder was installed between the south and north upper roofs. Sides rails will be painted dark brown at a latter date to minimize visual impact from pedestrian elevation.

PV panel circuits boxes installed on clerestory wall to service PV array that will be installed on south upper roof.

I have allowed for three PV panel circuits which will allow maximum flexibility to upgrade the PV array capacity by future home owners. The forth junction box could accept a wind generator circuit. Boxes are well proud of siding to allow PV circuit water-tight connections to side of boxes.

Finished installation ready for connection to PV Array

I have also allowed for electrical power, water hose, and compressed air supply to both the upper and lower roof levels.  This will assist on maintenance of the roof surfaces in the future. The air works well to blow off the cedar needles without removing the granules from the torch-on roofing. The difficulty with these penetrations is that they need to be installed before the exterior insulation and siding so that they can be air and water sealed at the WRB membrane level.

Fabricate an air port using an outdoor electrical cover

Air supply top right, water below, electrical bottom left, will aid in maintenance to roof surfaces down road.

Installation of high capacity 3″ Lindab steel downspouts from Precision Gutters provide a clean modern exit of storm water from the roof surfaces to the municipal storm sewer.

Underground poly gas lines installed from the remote meter location (special permission required from utility for remote location) on south elevation to the north elevation where back-up generator will be installed.

Poly gas line was run inside perforated Big-O as a sleeve where it was run through gravel (about the only thing Big-O is good for!). White PVC is storm drain for roof runoff. The wye in foreground will service a surface sidewalk drain.

Originally I was going to install a diesel back-up generator (with remote thoughts of converting to burn used veg oil, like my truck, at some future point), but with a full tank providing less than two days of coverage, I instead decided to install a natural gas generator. The yearly connection fees to the utility are well under $200,  so well worth convenience.  And a  NG unit is cheaper, will burn much cleaner than Diesel, and will be quieter.  To offset the noise in close proximity of the neighbour, they will be provided an outdoor plug to utilize in power outages that will keep their heating system and some lights running.

I also prototyped and then installed permanent soffit light for the upper north roof (other roofs to follow as time permits). We elected to install continuous LED light strips to provide an even glow that is dimmable. Neither my wife or I are a fan of pot lights in this application.

24 VDC strips applied to back of fascia framing. Later a flashing will be installed at base of fascia that covers the bottom surface of these lights so that they are hidden from sightlines below.

The LED light strips were applied to the wooden framing with a bead of silicone to provide a lasting connection.  The included self adhesive strip pulls away from even pained framing in a day or two.  The strip was also fasted every few feet with a screwed-in clip.

The soffit lighting strips are visible in this photo on the upper north roof. They are dimable and provide a nice even glow along the soffit length for a warm inviting feel.

 

Finally, I also installed the air tight door that will separate the main portion of the basement from the cold room/metal work shop below the garage.  In the photo below, you can also see the 5ft x 8ft door that will be installed at the basement exit to side yard walk-up stairs.  This will allow large projects from the wood shop to exit the house easily and also allow the installation of large water storage tanks for the Hydronic heating/cooling system.

The door on right leads to the cold room under the garage. When completed it will provide an R6 insulated and air tight separation between these two spaces.

With the majority of the exterior building envelope behind me, I will now turn to the interior of the dwelling. The first task will be to insulate the roof assembly and install the sealed plywood air barrier on the underside of the roof trusses.  The ROCKWOOL insulation package will be arriving this coming week (Thank-you to ROCKWOOL for their continued support of this build).

This will then allow me to finally introduce some heat into the building (temp electric heaters). On that thought, I am also thrilled to advise I have entered into an agreement with Daniel Schlicher of DS Design Consultants (on advise from John Siegenthaler) to assist me in designing the hydronic heating and cooling system for this dwelling.  I am using LoopCAD (thank you to Brad McCrea of Avenir Software for providing this at a heavy discount) to model the dwelling, determine accurate heat losses per room, and design the room by room hydronic heating panels that will be installed generally in the ceilings. Daniel will then design the piping and control system for the heating/cooling plant using an Air to Water Exterior Heat Pump.  It is a huge relief to have the personnel for this component design nailed down!

PS: Preliminary calculations show the total heating load for over 4500 sq ft will be less than 20K Btu.  That is less than a fifth of a standard requirements for a code built house of this size.

With the vast majority of the structure, envelope, and exterior complete, I am hoping I am on the final lap of this journey.  I do not anticipate any of the outstanding utility rough-ins to provide significant roadblocks or extended labour requirements. So occupation of the dwelling is still hoped to be accomplished by late summer or early fall of this year.  Lets hope anyway!

As always, thanks for visiting and send me your comments.  I would love to hear from you!